Framing and MEP rough-in inspections are scheduled for tomorrow. Assuming everything passes the drywallers will starting turning the inside white. Wasn’t a Sunday night update last week because I just finished a 22 hour all night roofing marathon – the last 4 hours of which were spent in the rain finishing up the ridge cap. Basement level windows / doors are set now and some of the siding is up. Since last week the roof has made it thru 2 torrential downpours without a sign of a leak which isn’t bad for a bunch of guys who’ve never put on a standing seam roof before. If a leak shows I’ll call Kyle plumbing to make up a catch pan and run it to the nearest drain because I’m not renting a JLG again to get back up there. ~ Jason