Chimney is in so we now have a stainless steel spire sticking up. In the future we should be able to get good cell phone reception if we touch the fireplace. Will need to build a custom curb for the chimney because rubber boots don’t work on a 16:12 roof. Roofing has started finally - took about 2 hours to get the first piece set and trimmed out with all of the architectural cleats, standoffs, rivets, roll tape, etc. Only takes about 10 minutes to set a panel so it will start to go faster. Cedar soffits are complete at the NW end of the house. Varposhield is up at the basement area now.







































Jason hired some concrete finishers to come and work the poured concrete and they brought a machine to make it all smooth. After the concrete was finished on 11.12.11 Jason got a MUCH NEEDED day off on 11.13.11 for he and Wendy to go DUCK HUNTING! Wendy was a good girl. This is where my work day came in, I spent the afternoon out washing concrete and vaccuuming concrete to get it ready for the sealer. 